When things change
Scripts change after the crew has them, and someone always asks for one more day. Lock the script so the numbers hold, mark what changed, and see what a change costs in days and dollars before you say yes.
Why it matters
Once the crew has the script, everyone's paperwork points at its scene numbers. If a new scene renumbers everything after it, the call sheets, the shooting order and the props list all point at the wrong scenes. Locking keeps the numbers, so a new scene gets a letter and a cut scene keeps its place.
Every change also has a price. Moving one scene can bring an actor in for an extra day or save one. C-47 measures each change against the plan everyone agreed, so you can answer what does that cost? before you agree to it, and undo it if the answer is no.
Watch
Lock the script
On the Script screen, in Write mode, choose Lock scene and page numbers…. The app explains what locking means before it does it.

- Lock now fixes every scene and page number. Do it when the script goes out to the crew.
Next, choose Start blue revision. Every line you change from now on is marked with an asterisk in the right margin, as on a paper revision. The colors follow the usual order: blue, then pink, yellow, green, goldenrod and on, so the next one is Start pink revision.
Locking and starting a revision each save a version of the whole project by themselves (Script locked and Blue Rev. with the date), so you can compare later with what the crew had.
Add a scene, cut a scene
With the script locked, a scene typed between scenes 3 and 4 becomes 3A, not a new scene 4. To cut a scene, click in its heading: a red Omit this scene button appears in the line bar.

- Locked: scene and page numbers are fixed.
- Blue revision is on, and the chip reminds you that changed lines get an asterisk. Stop marking changes ends it.
- The new scene gets a letter: 3A, between 3 and 4.
- Omit this scene shows only in a locked script, with the cursor in a scene heading.
An omitted scene keeps its number with the word OMITTED, so nobody thinks scene 5 went missing. A page that runs over gets a letter too: here the new scene pushed the text past the end of page 1, so the app added page 1A and page 2 still starts where it did.

- Scene 3A in the list.
- Scene 5 stays in place as OMITTED.
- The asterisk marks a line changed in this revision. Headings don't get one.
- PAGE 1A: the extra page, so page 2 keeps its number.
Change requests: what will it cost?
The Last Light sample has an agreed plan saved as its baseline, Locked schedule and budget. Its log already holds one request, CR-01, approved before the plan was locked: the producer swapped two days so the app could drop the cook through his long gap (lesson 5). When someone asks for a change, open a request first on Changes and Collaboration, under Project in the sidebar.

- Open the request. From then on, everything you change anywhere in the app is part of it.
Then make the change where it belongs. Here, scene 32 moves in Shooting order: select its strip, and in the panel beside the board, choose another day in the On list. A bar across the top of every other screen reminds you a request is open.

- The open request. Review it goes back to it.
- Scene 32, with Maggie (#4) and the cook (#5), on day 2.
- Choose Day 13 here. The strip moves to the end of day 13, with the other diner scenes.
Back on Changes and Collaboration, the open request shows the change In days and dollars: shoot days, pages, cash and full value, and who works more or fewer days.

- The request's number, CR-02 (the sample's own CR-01 came first), and that it's still open.
- In days and dollars: the change since the request was opened. Cash drops by $220.00: one day of the cook's $200 rate, plus the 10% contingency on it.
- Why: the cook goes from 3 work days to 2, and from 7 paid days to 6. He's still held for the 4 days between day 13 and day 18.
- The same change measured against the baseline, the plan everyone agreed.
At the foot of the request, write a Decision note and choose Approve or Reject…. Rejecting asks first, then puts the project back exactly as it was before the request opened.

- Approve keeps the change and closes the request.
- Reject and undo puts every change in the request back.
- Keep it open goes back without deciding.
Either way, the request stays in the Log with what it asked for, who asked and what it changed or would have changed.
Versions and the baseline
Below the requests, Versions keeps named copies of the whole project. Type a name and choose Save a version when something is agreed; the first one you save becomes the baseline. Make baseline moves the label to another version, and Compare with now shows any version against the project as it is.

- Save a version: name it for what was agreed.
- The version marked Baseline is the one changes are measured against. Other versions have Make baseline.
- Compare with now fills the Compare card below.
- In days and dollars, then scene numbers and every record that changed.
Collab files: someone else works on a copy
- Type who it's for, then choose Make a collab file… and save the copy. Send it to them; they open it in their own copy of C-47.
- When it comes back, choose Bring back their file… on its row. You see each thing they changed and tick what to take, then choose Accept Revisions.
- If you both changed the same thing, you choose between Keep yours and Take theirs.
- What you take becomes one change request in the log, so it's measured and recorded like any other change.
Try it
Part 1: lock and revise The Late Bus
- Download The Late Bus (the-late-bus.fountain) from this course. On the start screen, choose Start from a script file… and open it.
- In the sidebar, choose Script. Check that Write is on.
- Choose Lock scene and page numbers…, read the explanation, then choose Lock now.
- Choose Start blue revision.
- Click at the end of scene 3's last line (…blink in the rain.) and press Enter. Type EXT. RUTH'S DINER – DAY and press Enter, then type a line of action, such as June helps Teo down the bus steps. Pepper jumps straight into a puddle.
- Look at the Scenes list: the new scene is 3A. Check that your new action line has an asterisk in the right margin.
- Click in scene 5's heading, INT. CITY BUS – NIGHT, and choose Omit this scene. Scene 5 now reads OMITTED.
Part 2: a change request in Last Light
- Choose Close project, then Close anyway (you don't need to keep The Late Bus). On the start screen, choose Open the sample film.
- In the sidebar, under Project, choose Changes and Collaboration. Under Change requests, type a title such as Diner scenes together and who asked, then choose Open the request. It becomes CR-02, because the sample's log already has CR-01.
- Choose Shooting order. Select the strip for scene 32 (Rosie's Diner, cast 4 and 5, on day 2). In the panel on the right, change the day list from Day 2 to Day 13, where the other diner scenes are.
- Choose Review it in the bar at the top. Read In days and dollars: the cook goes from 7 paid days to 6, and the cash drops by $220.00.
- Scroll down to Versions and choose Compare with now beside Locked schedule and budget. Read the same change measured against the baseline.
- Scroll back up to the request. Choose Reject…, then Reject and undo. Go to Shooting order and check that scene 32 is back on day 2.
Check your work


Quick check
Pick an answer to see why it is or isn’t right. Nothing is scored.
Question 1
The script went to the crew last week. The writer adds a new scene between 11 and 12. What should it be numbered?
Question 2
Your director asks to move a scene to another day because it's easier. What do you do first?
Question 3
You rejected a change request. What happens to the change it made?